Thanks to winter storm Juno, we got pushed back a week. Here's our schedule for next week:
    • Remaining of Week 7:
      • Monday 2/2/2015 : Finishing up odds and ends with framing & electrical

Week 8 will go as planned if, and only if, upcoming winter storm Linus doesn't postponed things for us. Here is that schedule:
    • Week 8 Schedule
      • Tuesday 2/3/2015 : City Inspection
      • Wednesday 2/4/2015 : Insulation - Part 1
      • Thursday 2/5/2015 : Insulation - Part 2
      • Friday 2/6/2015 : Drywall - Part 1
      • Saturday 2/7/2015 : Drywall - Part 2
      • Remaining days : Will know more later on.